Stage Overestimation

Employee: Alexander Fedorenko
Category: Projects->Remote Install Manager
Date: 6/14/2005

                Name                 Original estimation (hours) Current estimation (hours) Forecast under/over spend (hours) Time remaining (hours) Priority Deadline
Remote Install Manager 11 22.5 11.5 3   6/22/2005
  Test for shared hashtable in multithreading 2 2.5 0.5 2.5 Normal 6/22/2005
  Meetings 5 5 0 2.5   6/21/2005
    Stand-up meeting for RIM 5 5 0 5 Normal 6/21/2005
  Network access 0 5 5 -3   6/18/2005
    Show free space on all local drives Unplanned 5 5 5 Normal 6/18/2005
  User interface 4 10 6 4.1   6/20/2005
    Enable/Disable install pane 4 4 0 3 Normal 6/17/2005
    Specify components to install Unplanned 6 6 6 Normal 6/20/2005

 
 
Employee Signature Date
 
Manager Signature Date